Projects

A Multidisciplinary engineering and design consultancy

We have been engaged in design aspects of various Transport Infrastructure Projects through all their design development phases. The designs carried out in various capacities include earthworks & bridges, hydrology & hydraulic studies, geotechnical studies, railway track alignment, road pavements, railway operation modelling, signalling & communication studies, overhead line equipment studies, constructibility reviews, planning & scheduling, CAPEX & OPEX studies and preparation of reports at various stages from concept to commissioning.

Location : Karimnagar, Telangana, India.
Client : Ms.Navayuga  Engineering Company Ltd.
Start date : Nov 2008
End date : Apr 2019
Project Details : Detailed Engineering services.

Location : Ananthapuramu, Andhra Pradesh, India
Client : New & Renewable Energy Development Corporation of Andhra Pradesh, Vijayawada
Start date : Nov 2020
End date : July 2021
Project Details : 500 MW Pumped Storage Hydro Electric Project, Feasibility Study & Detailed Project Report

Location : Andhra Pradesh, India
Client : Andhra Pradesh Municipal Development Project
Duration : December 2018
Project Details : Preparation of Basemap, Updation of Revenue Database and Rationalisation of House Numbering. Preparation of GIS Base maps, Revenue Database updation Survey and Digital Door Numbering.

Location : East Coast, East West and North South Corridors
Client : DFCCIL
Duration : March 2023
Project Details : Preparation of Detailed Project Report and Final Location Survey for DFCC corridors.
East Cost Corridor – 1115km.
East West Corridor – 1868km.
North South Corridor – 931km Route Length.

Location : Delhi – Varanasi & Lucknow – Ayodhya – 945 km Route Length.
Delhi – Amritsar & Sangrur – Chandigarh 525 km Route Length.
Chennai – Mysore – 450 km Route Length.
Client : National High Speed Rail Corporation.
Duration : March 2023
Project Details : Final Alignment Design for New NHSRCL High Speed Rail Corridors.

Location : Queensland, Australia
Client : Adani Mining Pty Ltd
Duration : February 2020 – September 2020.
Project Details : Detailed Design work including Civil, H&H, Alignment, Drainage, Geotech, Bridges, Culverts for 200 km of rail line.

Location : Queensland, Australia
Client : Fulton Hogan
Duration : January 2016 – June 2016
Project Details : Design and construction of 2 QR timber bridge replacement of Kings Bridge (72m long) and German Bridge (15m long).

Location : Queensland, Australia
Client : Adani Mining Pty Ltd, Austra alia
Duration : October – November 2014
Project Details : Adani Mining is proposing to develop thermal coal mine in North Galilee Basin, Central Queensland. For the effective operation of mine, suitable road link to the major regional centres of Townsville, Mackay and Rockhampton must be established. This project consists of design of 90 km long road between Elgin-Moray Road and Moray- Carmichael Road which is at present a rural unsealed road. Design works for hydrologic, hydraulic and structure design were undertaken.

Location : Varsity to Queensland, Australia
Client : Seymour Whyte Constructions Pty Ltd.
Duration : January 2020.
Project Details : Material Take off/Quantity estimation.

Location : Mumbai – Ahmedabad
Client : National High Speed Rail Corporation Limited.
Duration : 2025 estimated.
Project Details : Project Management Consultant of Route Length : 510 km (approx.)

PROJECT IMAGES